PMP认证考试试题精选(3)

文章作者 100test 发表时间 2007:01:15 18:41:57
来源 100Test.Com百考试题网


41. Determining what resources and quantities will be used for the project is part of
A. Cost budgeting
B. Cost estimating
C. Resource planning
D. Cost control

42. The Scope Statement is used in which process
A. Resource Planning
B. Cost Estimating
C. Cost Control
D. Cost Planning

43. Inputs into Resource Planning include:
A. Staffing requirements, procurement policies, Work Breakdown Structure
B. Work Breakdown Structure, Scope Statement, historical information, resource pool description, organizational policies
C. Work Breakdown Structure, Scope definition, resource pool description
D. Expert judgement, historical information, Work Breakdown Structure, Scope Statement

44. The term resource planning refers to:
A. Labor
B. Capital equipment
C. Materials
D. All of the above

45. Cost estimating includes all of the following except:
A. Identifying and considering various costing alternatives
B. Pricing strategy
C. Developing an assessment of the likely quantitative result
D. Baselining

46. Cost Estimating is most closely linked with which other process?
A. Procurement, Risk
B. Scope, Procurement
C. Time, Scope
D. Risk, Time, Integration

47. Parametric Modeling and Analogous Estimating are used in what process:
A. Cost Control Tools and Techniques
B. Cost Estimating Tools and Techniques
C. Risk Analysis Tools and Techniques
D. Risk Analysis Outputs

48. You are building the budget for your project. You dont have detailed requirements for the project yet. However, a fellow project manager completed a similar project A year ago, and has his budget assumptions and final costs documented. You decide to use this information as the basis of your cost estimating. This is called:
A. Analogous estimating
B. Parametric modeling
C. Bottom-up estimating
D. Spreadsheeting

49. As the Project Cost Engineer on a high rise development you are preparing your budget. You have developed a template, based on similar projects that can be used for buildings with 3-25 tories. It breaks out cost per square foot for plumbing, wiring, HVAC, dry wall, floors etc. This type of cost estimating is called:
A. Analogous estimating
B. Parametric modeling
C. Bottom up estimating
D. Spreadsheeting

50. Before you begin the cost budgeting process for building a new school you should make sure your cost engineer has given you:
A. Cost estimates, chart of accounts, cost baseline
B. Supporting detail, estimate at completion
C. Cost estimates and supporting detail,
D. Cost management plan, cost change control plan, cost baseline

相关文章


项目管理案例:赢与非输之别
NB-PMM法在项目综合管理中运用实例(一)6
项目管理案例:疲惫不堪的老累狗
PMP认证考试试题精选(3)答案
PMP认证考试试题精选(3)
项目管理案例:发射时间
50倒霉企业家--政策风险
PMP认证考试试题精选(2)
蒙牛是榜样--三位创业者的苦与乐
澳大利亚华人论坛
考好网
日本华人论坛
华人移民留学论坛
英国华人论坛